8-1-20 fdl weekly construction schedule

  1. Rees Street from N. Main Street to N. Macy Street and Fond du Lac Police Department (PD) Parking Lot

Schedule: July 2020 through August 2020
Description: The project includes roadway reconstruction, excavation, grading, sidewalk and approaches, restoration/landscaping and lighting. The Police Department parking lot reconstruction will replace asphalt pavement, deteriorated sidewalk and curbing along with moving the flagpoles and adding parking stalls.
August 3 to August 7: Crews will complete the majority of the grading along Rees Street. The electrical contractor will install conduit and lighting bases along Rees as well. The concrete crew will start slip forming the curb and gutter along Rees Street and the PD parking lot.
Traffic Impacts: W. Rees Street and the Police Department parking lot will be closed to through traffic. Residents, business owners, and customers can past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. However, please utilize access off N. Main St. or N. Macy Street as all properties except for the Police Department parking are accessible off these streets. Access to the Police Department parking lot will be closed, but the Emergency After-Hours Entrance on the northwest corner of the Police Department Parking Lot will remain open. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades if not accessing businesses. Parking is not permitted in the PD parking lot or on the street within the construction zone during working hours.

  1. Military Road from Oak Park Avenue to S. Hickory Street

Schedule: March 2020 through October 2020
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, and restoration/landscaping.
August 3 to August 7: The concrete contractor will continue setting string line and fine grade the southeast lane between Hickory Street and Oak Park and plans to place the lane midweek.
Traffic Impacts: S. Military Road remains closed to through traffic from S. Hickory Street to Seymour Street.  Residents, business owners, and customers may access properties and businesses past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours. Motorists are asked to please use caution when driving through this construction area.
11 th Street from Park Ave to Martin Avenue
Schedule: May 2020 through October 2020
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, and restoration/landscaping.
August 3 to August 7: The utility contractor will have two crews replacing water and sanitary sewer laterals throughout the week.
Traffic Impacts: 11 th Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Hazotte Court from Division Street North to Dead End
Schedule: May 2020 through October 2020
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, and restoration/landscaping.
August 3 to August 7: No work at this time.
Traffic Impacts: Hazotte Court remains open to traffic.
Follett Street from Doty Street to Military Road
Schedule: May 2020 through October 2020
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, and restoration/landscaping.
August 3 to August 7: The concrete contractor will begin setting the curb string line and may potentially pour the curb later in the week.
Traffic Impacts: Follett Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
County Road V/Fond du Lac Avenue/National Avenue
Schedule: March 2020 through October 2020
Description of work: The project includes reconstruction of the water main and services and partnership with Fond  du Lac County for new storm sewer, street, pedestrian trail, and lighting.
August 3 to August 7: The contractor plans to begin constructing the concrete curb and gutter.
Traffic impacts: The intersections of County Road V/Fond du Lac Avenue/National Avenue remain closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs.
Project Detour: Signed detour in place utilizing Pioneer Road, Martin Avenue, and Ninth Street

Related Posts

Loading...