- Rees Street from N. Main Street to N. Macy Street and Fond du Lac Police Department (PD) Parking Lot
Schedule: July 2020 through August 2020
Description: The project includes roadway reconstruction, excavation, grading, sidewalk and approaches, restoration/landscaping and lighting. The Police Department parking lot reconstruction will replace asphalt pavement, deteriorated sidewalk and curbing along with moving the flagpoles and adding parking stalls.
August 17 to August 21: Crews will start forming and pouring the concrete sidewalk and aprons along Rees Street and in the PD parking lot. Fine grading of Rees Street and PD parking lot should start by weeks end.
Traffic Impacts: W. Rees Street and the Police Department parking lot will be closed to through traffic. Residents, business owners, and customers can past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. However, please utilize access off N. Main St. or N. Macy Street as all properties except for the Police Department parking are accessible off these streets. Access to the Police Department parking lot will be closed, but the Emergency After-Hours Entrance on the northwest corner of the Police Department Parking Lot will remain open. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades if not accessing businesses. Parking is not permitted in the PD parking lot or on the street within the construction zone during working hours.
- Military Road from Oak Park Avenue to S. Hickory Street
Schedule: March 2020 through October 2020
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, and restoration/landscaping.
August 17 to August 21: The concrete contractor will continue setting string line and fine grade the southeast lane between Hickory Street and Oak Park and plans to place concrete on Tuesday. Contractor intends to set string line for curb on side streets and/or begin pouring drive approaches/sidewalk later on in the week.
Traffic Impacts: S. Military Road remains closed to through traffic from S. Hickory Street to Seymour Street. Residents, business owners, and customers may access properties and businesses past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours. Motorists are asked to please use caution when driving through this construction area.
11 th Street from Park Ave to Martin Avenue
Schedule: May 2020 through October 2020
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, and restoration/landscaping.
August 17 to August 21: The utility contractor will continue storm sewer installation in between Vine Street and Martin Avenue and begin placing catch basins and storm sewer laterals.
Traffic Impacts: 11 th Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Division Street from Park to Hazotte Court and Hazotte Court from Division Street North to Dead End
Schedule: May 2020 through October 2020
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, and restoration/landscaping.
August 17 to August 21: Underground utility contractor will begin laying new water main midweek on Division Street from Park Avenue to Hazotte Court and then on Hazotte from Division Street to the dead end.
Traffic Impacts: Division Street from Park Avenue to Hazotte Court and Hazotte Court will be closed to through traffic starting Wednesday, August 19. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Follett Street from Doty Street to Military Road
Schedule: May 2020 through October 2020
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, and restoration/landscaping.
August 17 to August 21: The concrete contractor will pour concrete drive approaches and sidewalk during the week.
Traffic Impacts: Follett Street is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
County Road V/Fond du Lac Avenue/National Avenue
Schedule: March 2020 through October 2020
Description of work: The project includes reconstruction of the water main and services and partnership with Fond du Lac County for new storm sewer, street, pedestrian trail, and lighting.
August 17 to August 21: The contractor plans to complete the concrete sidewalk, and then following that the terrace will be top soiled.
Traffic impacts: The intersections of County Road V/Fond du Lac Avenue/National Avenue remain closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs.
Project Detour: Signed detour in place utilizing Pioneer Road, Martin Avenue, and Ninth Street